Overall Progress: 18%

Lifecycle Timeline

Total of 22 milestones defined for the construction phase.

CompletedIn ProgressLocked

Step 01

Roof Access Staging

Completed

Duration

Feb 01 — Feb 03, 2026

Key Deliverable

Safety Access Approval

Step 03

Deck Preparation

Completed

Duration

Feb 04 — Feb 06, 2026

Key Deliverable

Deck Condition Log

Step 04 • Current

Roof Underlayment Installation

In Progress

Duration

Feb 03 — Feb 18, 2026

Key Deliverable

Weatherproof Base Layer

Step 05

Flashing Integration

Locked

Target Start

Feb 19, 2026

Key Deliverable

Flashing Compliance Report

Step 06

Shingle Installation

Locked

Est. Start

Feb 23, 2026

Key Deliverable

Roof Finish Inspection