Project All Milestones Overview

Overall Progress: 68%

Lifecycle Timeline

Total of 22 milestones defined for the construction phase.

CompletedIn ProgressLocked

Step 01

Power Audit & Routing

Completed

Duration

Jan 03 — Jan 11, 2026

Key Deliverable

Existing Load Map

Step 14

Control Room Wiring

Completed

Duration

Jan 12 — Jan 18, 2026

Key Deliverable

Control Rack Compliance

Step 15 • Current

Power Systems Integration

In Progress

Duration

Jan 16 — Jan 30, 2026

Key Deliverable

Thermal Scan Package

Step 16

Commissioning Validation

Locked

Target Start

Feb 01, 2026

Key Deliverable

Commissioning Certificate

Step 17

Client Handover

Locked

Est. Start

Feb 05, 2026

Key Deliverable

Operations Training Pack

Future Phases

Steps 18 through 22 are scheduled for Q1 2027